dc.description.abstract | This paper studied factors that caused delay to the GIBE III hydroelectric power project.
Using data collected from 63 former and current employees of the GIBE III Hydroelectric
Power Project. Accordingly, the ranks of delay factors are as follows. Lack of finance,
Improper planning, Inadequate quality procedure, Design change and unforeseeable
circumstances. The research study considered a population of 75 to collect data using
census survey. Structured questionnaire and secondary data were also used to collect data.
The Data were analyzed using multiple linear regression method. Subsequently, it was
determined that Lack of Finance (LOF), Inadequate Quality Procedure (IQP), Design
Change (DC), Unforeseeable Circumstances and Improper Project Implementation had
negatively impacted the GIBE III hydroelectric power project by causing delay to the
project. | en_US |
dc.language.iso | en | en_US |
dc.publisher | ST. MARY’S UNIVERSITY | en_US |
dc.subject | GIBE III Hydroelectric Power Project, Factors of Delay, Project Delay, Ethiopia. | en_US |
dc.title | Factors of Project delay: In the Case of the Gibe III Hydroelectric Power Project. | en_US |
dc.type | Thesis | en_US |
Appears in Collections: | Project Management
|